How to use this calculator
- Measure the length and width of the area to fill or excavate.
- Enter the intended material depth. Use the unit shown beside the field; inches and centimeters are available for shallow layers.
- Leave the allowance at zero for pure volume, or add a project-specific percentage before planning the order.
Measure the project correctly
Measure inside containment edges or forms for fill volume. An outside-to-outside measurement can overstate the amount.
Average depth can hide major dips. For uneven sites, divide the area into sections with similar depths, calculate each, and sum the unrounded volumes before placing an order.

The calculation
The same geometric calculation is used internally by material estimators on this site. Metric dimensions are calculated in meters; 1 m³ is about 1.308 yd³.
The displayed order amount rounds upward to 0.1 yd³ or 0.1 m³. That is a planning increment, not a claim about a supplier’s minimum order.
Worked example
A rectangular 12 ft by 10 ft area needs a 3 in layer. Start with no allowance and assume a material price of $50 per cubic yard.
| Step | Calculation | Result |
|---|---|---|
| Convert depth | 3 in ÷ 12 | 0.25 ft |
| Find cubic feet | 12 × 10 × 0.25 | 30 ft³ |
| Convert to yards | 30 ÷ 27 | 1.11 yd³ |
| Plan order | Round 1.111 up to 0.1 yd³ | 1.2 yd³ |
| Price material | 1.2 × $50 | $60 |
The exact rectangular volume is 1.11 yd³; 1.2 yd³ is a practical tenth-unit order figure. If you add waste, the rounding happens after the allowance.
How to read the result
- Measured volume
- Dimensions multiplied without a material allowance.
- Unit conversions
- The same raw volume shown in cubic feet, cubic yards, and cubic meters.
- Order amount
- The allowance-adjusted volume rounded upward to a tenth.
Before you buy materials
Use Concrete for a pour-specific estimate, or Gravel when an approximate weight is also useful.
A material sold by the ton needs a density or supplier conversion; cubic yards alone do not establish tonnage.
When adding several sections, combine exact volume before rounding to avoid accumulating unnecessary tenths.
Common estimating mistakes
- Forgetting to convert inches to feet: Use the depth input unit or enter a full value such as 3 in.
- Assuming volume equals weight: Material density is needed for a weight estimate.
- Rounding each segment independently: Add exact segment volumes, then apply allowance and purchase rounding once.
Assumptions and limits
- One rectangular prism with constant depth; slopes and irregular cross sections are not modeled.
- Material-specific expansion, settlement, compaction, density, delivery charges, and labor are excluded.
Frequently Asked Questions
Common questions about the Cubic Yard Calculator.
- How many cubic feet are in a cubic yard?
- Exactly 27 cubic feet. The calculator displays both units from the entered dimensions.
- Can I calculate excavation instead of fill?
- Yes for a rectangular excavation. This gives geometric bank volume only; hauling or loose-volume swell is material specific.