How to use this calculator
- Measure the gross wall length and height, then total the area of large openings that will contain no block.
- Use the actual exposed block face dimensions and planned mortar joint. The starting 15 5/8 × 7 5/8 in face with a 3/8 in joint is an editable example.
- Add a cutting allowance. Enter blocks per pallet only when you have the supplier’s actual pack count, then choose block or pallet pricing.
Measure the project correctly
Measure the face being laid, not block depth. A nominal 8 × 8 × 16 in unit can have a smaller specified face because the nominal dimensions allow for mortar joints. Check the chosen product rather than treating the starting inputs as universal.
Subtract openings once from gross wall area. For walls that change height or use different block sizes, calculate each section separately and combine the whole-unit requirements before ordering.
Planning a 10 × 10 ft wall? Read the worked concrete-block count to compare block equivalents, course cuts, and a whole-unit order.

The calculation
The joint is added to both exposed face dimensions before dividing area. This is an area method: it does not lay out each course or credit reusable cuts.
Recommended blocks = round up[base blocks × (1 + waste ÷ 100)]. If a pallet count is entered, recommended pallets = round up(recommended blocks ÷ blocks per pallet). A per-block rate with pallets entered prices all blocks in full pallets.
Worked example
For a 20 ft by 8 ft wall with 20 ft² of large openings, use an illustrative 15 5/8 × 7 5/8 in block face, 3/8 in joints, and 5% waste. Suppose the supplier offers 90 blocks per pallet at $450 per pallet.
| Step | Calculation | Result |
|---|---|---|
| Net wall face | 20 × 8 − 20 | 140 ft² |
| Effective module | (15.625 + 0.375) × (7.625 + 0.375) | 16 × 8 = 128 in² |
| Base blocks | 140 × 144 ÷ 128; round up | 158 blocks |
| Add waste | 158 × 1.05; round up | 166 blocks |
| Whole pallets | 166 ÷ 90; round up | 2 pallets |
| Material cost | 2 × $450 | $900 |
Two pallets contain 180 units. Ask whether the supplier will sell the needed 166 blocks loose or accept returns; the calculator cannot infer those terms.
How to read the result
- Calculated requirement
- Whole block faces needed by the net-area module method before waste.
- Waste blocks
- Extra whole units added by the editable cutting allowance.
- Recommended purchase
- Whole loose blocks or pallets based on the actual supplier pack count entered.
Before you buy materials
CMHA distinguishes nominal and specified concrete masonry dimensions. Confirm the exact manufacturer unit and joint specification before ordering.
If the wall has several wythes or a return, estimate each relevant face or follow a project-specific masonry takeoff; a single wall rectangle will omit those units.
For a segmental retaining wall, use the Retaining Wall Calculator instead: it counts face blocks by course and has different assumptions.
Common estimating mistakes
- Adding a joint to nominal dimensions: Enter the actual exposed face before adding the joint; nominal dimensions may already include a joint allowance.
- Pricing the base count: Use the waste-adjusted block count or rounded pallets for the optional material price.
- Treating an area count as a block layout: Review corners, cuts, bond, reinforcement, and openings against the actual wall drawings.
Assumptions and limits
- One exposed wall face, uniform block and joint dimensions, and one large-opening deduction. Corners, bond changes, lintels, grout, reinforcement, mortar quantity, and labor are outside the face count.
- This quantity estimate does not determine structural stability, reinforcement, foundation, or code compliance. Use the project design and qualified local guidance for those matters.
Frequently Asked Questions
Common questions about the Concrete Block Calculator.
- Does this calculate mortar or grout?
- No. It counts block faces only; mortar and grout require product- and wall-specific volumes.
- Can I use a nonstandard block?
- Yes. Replace the example face dimensions and joint with the actual selected unit and planned layout.